AURYN Mining Corporation Shareholder Update

AURYN Mining Corporation (OTC: AUMC) has secured $4.5 million in Glencore financing to complete processing plant construction and mine infrastructure at Fortuna. The plant has advanced to integrated commissioning and initial production testing, while underground mine development continues. Priorities for the fourth quarter include stable plant operations, underground infrastructure, and expanded mining authorization.

ACCOMPLISHMENTS

Glencore Offtake Financing

AURYN and Glencore have agreed to definitive terms for an offtake arrangement covering 100% of the gold and silver concentrates produced from the Fortuna Project by AURYN and its subsidiaries over the life of the mine. Under the arrangement, AURYN has secured $4.5 million in financing to complete processing plant construction and mine infrastructure. The financing will be repaid over time through production.

Processing Plant

The plant has advanced to integrated commissioning and initial production testing. Its main circuits can now operate together, including continuous crushing and grinding, integrated flotation, tailings transfer to the tailings storage facility (“TSF”), and concentrate handling. Stable, sustained operation at the planned production rate has not yet been demonstrated, and full commissioning is not yet complete.

During the third quarter of 2026, installation of piping, pumps, and electrical systems was completed. Major components, including crushing, grinding, flotation, and the filter press, have progressed through mechanical and electrical completion and operational testing with ore and slurry. Filter press testing began on September 25, 2026, progressing from dry testing to wet testing.

Current work focuses on optimizing the crushing and grizzly circuit, flotation air balance, material flow, and concentrate dewatering. The filter press is undergoing further trials to improve concentrate cake consistency and dewatering performance. Concentrate has been temporarily placed in geotubes while filter press testing and adjustments are completed.

Initial tailings have been transferred to the TSF, where drainage and operating controls are being evaluated. Water recovery remains a critical priority as the plant’s water management system is optimized. Civil works are in the design stage, with containment walls, sumps, and water channels planned for construction during the fourth quarter of 2026.

The current commissioning target for the ball mill is approximately 5 tonnes per hour. Work continues to progressively achieve this throughput, resolve remaining equipment constraints, and improve equipment reliability, material flow, water recovery, and overall process stability. Reliable continuous operation must be demonstrated before full commissioning is considered complete.

Mine Development

Underground mine development continues under the approved 1,000-tonne-per month permit, with ongoing work to expand access and establish the infrastructure required to support future production.

Two water pumps are now in place, and development of a ramp at a positive 12% gradient has commenced to provide access to veins at the 1,875-metre level. A new ventilation raise is also under development to increase airflow within the mine.

Mine planning during the quarter also identified the need for a new emergency escape route connecting the 1,875-level crosscut with the ventilation raise, together with development of the associated sublevel. These works are important components of the mine’s ongoing development and underground safety infrastructure.

An electrical system has been designed for installation during the fourth quarter of 2026 to provide power for ventilation equipment and pumps, supporting improved underground operating conditions.

The current objective is to develop the critical underground infrastructure needed to support five to six active working faces at any given time, improving operational flexibility and providing a more consistent supply of ore to the processing plant.

Permitting

Fortuna Mining Authorization

The Fortuna Project’s permit for mining at 1,000 tonnes per month using the cut-and-fill method was approved on April 29, 2026.

On December 23, 2025, an application was submitted to increase Fortuna’s authorized mining capacity to 3,000 tonnes per month. The project encountered several challenges, and AURYN is reapplying for authorization at 3,000 tonnes per month with new parameters and standards for safety and efficiency.

Camp and Land-Use Permitting

During the third quarter of 2026, AURYN continued advancing the permitting process for the proposed mining camp and associated plant facilities. On October 1, 2026, the project documentation was presented to the Regional Authorities as part of the process to obtain the required Favorable Report for Construction on Land Outside Agricultural Use. The submission supports the formal review of the proposed facilities and their relationship with the existing authorized mining operation. AURYN will continue working with the relevant authorities to address any observations and advance the permitting process.

Supporting Infrastructure and Operations

Access Road Improvements

In July 2026, severe weather brought significant rainfall, flooding, landslides, and transportation disruptions to central and southern Chile, including the Metropolitan Region. The Fortuna access road became effectively impassable, significantly restricting site access for approximately two weeks and substantially reducing activities at Fortuna.

AURYN rapidly mobilized heavy equipment and established a contractor program to clear substantial amounts of debris and rebuild and strengthen sections of the road foundation. The road has been restored to good operating condition and supports normal access to Fortuna, providing a stronger foundation for continued mine development, plant commissioning, and future operations.

Sample Preparation Facility

AURYN is advancing plans to establish an on-site sample preparation facility using existing equipment. Samples will be prepared at Fortuna and sent to external laboratories for final analysis. This initiative is intended to reduce preparation costs, improve turnaround times, and provide more timely metallurgical data to support mine planning and processing plant optimization.

Employees

AURYN and its subsidiary currently employ 63 personnel supporting mine operations, plant commissioning, project development, environmental management, and corporate activities.

Community and Regulatory Engagement

AURYN continues to engage constructively with local communities and regulatory authorities as we advance the permitting process for the Fortuna Project. We remain focused on regulatory compliance and advancing the project’s supporting infrastructure.

OUTLOOK

During the fourth quarter of 2026, AURYN’s priorities are to advance the Fortuna Project toward stable operations, improve plant reliability, and strengthen underground mine development.

Key priorities include:

  • Optimize integrated plant operations, water recovery, and material handling.
  • Develop underground infrastructure to support five to six active working faces.
  • Advance the design, planning, and development of the underground escape route and associated sublevel.
  • Advance the 3,000-tonne-per-month mining authorization.
  • Complete critical road, water management, and site infrastructure improvements.
  • Maintain a strong focus on safety, regulatory compliance, and cost control.

AURYN remains focused on establishing reliable operations and building a sustainable foundation for long-term production and shareholder value.

STAY CONNECTED

For further details and to receive updates by email, please visit our website and subscribe to notifications. We appreciate your continued support and confidence in AURYN Mining Corporation.

FORWARD-LOOKING STATEMENTS

This news release contains certain forward-looking statements within the meaning of the United States Securities Exchange Act of 1934, as amended. This forward-looking information includes, or may be based upon estimates, forecasts and statements of management’s expectations with respect to, among other things, the completion of transactions, the issuance of permits, the size and quality of mineral resources, future trends for the company, progress in development of mineral properties, future production and sales volumes, capital costs, mine production costs, demand and market outlook for metals, future metal prices and treatment and refining or milling charges, the outcome of legal proceedings, the timing of exploration, development and mining activities, acquisition of shares in other companies and the financial results of the company. There can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially and substantially from those anticipated in such statements. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Inferred mineral resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that mineral resources will be converted into mineral reserves.